In software cost estimation, the COCOMO model primarily uses which input to estimate development effort?

589Medium DSSSB TGT Computer Science 0 replies 1 views
0
In software cost estimation, the COCOMO model primarily uses which input to estimate development effort?
  • AThe number of function points only
  • BThe estimated size of the software in KLOC (thousands of lines of code)
  • CThe number of developers available
  • DThe programming language's release year
Correct answer: B